Karatsu Data Bank

Offshore Wind Power: Disadvantages, Problems and Capacity 202692.5 GW worldwide, China first (end of 2025). Japan's zones, withdrawals, decommissioning costs and Saga

Offshore wind turbines seen from the shore at Zenibako, Otaru, Hokkaido
Global offshore wind capacity92.5 GWend of 2025 (GWEC 2026)
Largest marketChina 52.3%48.4 GW (GWEC 2026)
Japan's designated zones38 zones12 promotion, 9 promising, 17 preparatory (as of 5 Jan 2026)
Delayed by withdrawalabout 1.7 GWthree Round 1 sites (Agency for Natural Resources and Energy)

What are the disadvantages and problems of offshore wind power?

A Ministry of the Environment study group report (March 2023) lists noise, turbidity, birds, marine mammals, fish, benthic animals, seaweeds and seagrasses, and landscape among the items assessed for fixed-bottom offshore wind, and names noise, birds and marine life as items of particular concern in the Environment Minister's opinions (Ministry of the Environment, report of the FY2022 study group on environmental impact assessment for offshore wind, p. 5). In Japan, Mitsubishi Corporation, which led the consortium selected for three Round 1 sites, announced on 27 August 2025 that it would stop developing them (ANRE, Offshore wind power, Oct 2025, p. 2), delaying about 1.7 GW of capacity (Agency for Natural Resources and Energy (ANRE), Offshore wind power, 26 Dec 2025, p. 16). Global offshore wind capacity reached 92.5 GW at the end of 2025, 52.3% of it in China (GWEC, Global Offshore Wind Report 2026).

This page was made by Karatsu Farm & Food as part of the Karatsu Data Bank. It sets out offshore wind power and its disadvantages and problems using figures and statements from public sources: the world (ranking and trend by country), Japan (zones by prefecture, selections by round, plants in operation, environmental impact assessment, birds, fisheries, decommissioning, withdrawal and generation cost), Saga and Karatsu. A review of research on ecological impacts, the history of the waters off Karatsu and Saga Prefecture's Q&A are on Renewable energy and biodiversity (the IPBES Nexus Assessment and Karatsu).

QuestionFigurePeriodSource
Global cumulative capacity92.5 GWend of 2025GWEC p. 35
New global capacity in 20259.3 GW2025GWEC p. 35
Largest marketChina 52.3% (48.4 GW)end of 2025GWEC pp. 36, 38
Japan's cumulative capacity0.3 GWend of 2025GWEC p. 38
Japan's zones12 promotion, 9 promising, 17 preparatoryas of 5 Jan 2026ANRE
Decommissioning cost at tender stage70% of offshore construction costRound 3 tender guidelinesMETI and MLIT
Sea eagle collisions with wind turbines (incl. onshore)73FY2003-FY2021Ministry of the Environment
Generation cost of fixed-bottom offshore wind¥30.9/kWh (2023), ¥14.0/kWh (2040, base case)incl. policy costsGeneration cost working group
Offshore wind turbines are either fixed-bottom, with foundations on the seabed, or floating. In Japan's general sea areas the government sorts zones into preparatory, promising and promotion zones, and selects developers by tender in promotion zones.

Offshore wind capacity by country (end of 2025)

GWEC reports that 9.3 GW of new offshore wind was grid-connected worldwide in 2025, 16% more than the year before, bringing the total to 92.5 GW, or 7.1% of all wind capacity. Asia Pacific had 53.5 GW (58% of the world), Europe over 38 GW (42%) and North America 174 MW, all in the United States (GWEC 2026, pp. 35, 38). Floating wind totalled 278 MW (5 MW in Japan), and 2025 was the first year since 2015 with no new floating capacity (p. 39).

RankCountry/regionShare of cumulative (end 2025)Cumulative (GW)Share of cumulative (end 2024)
1China52.3%48.450.3%
2United Kingdom18.4%about 17.019.2%
3Germany10.4%about 9.610.9%
4Netherlands5.3%about 4.95.9%
5Taiwan3.9%3.63.7%
6Denmark2.9%about 2.73.2%
7Belgium2.4%about 2.22.7%
8France2.1%about 1.91.8%
9Vietnam0.9%0.91.1%
Others (incl. Japan, South Korea, US)1.2%about 1.11.2%
(of which Japan)-0.3-
(of which South Korea)-0.3-
World100%92.5100% (83.2 GW)
GWEC shows cumulative capacity by country as pie-chart shares. China 48.4, Taiwan 3.6, Vietnam 0.9 (intertidal) and Japan and South Korea 0.3 GW each are from the report text; other GW values are 92.5 GW × share, our calculation. Ranks are our sorting of end-2025 shares, down to Vietnam in 9th. Japan and South Korea (0.3 GW each) are included in "Others" in the chart, so they are shown on separate rows (Japan in bold). Sweden (0.2%), shown separately in the chart, is smaller than Japan and South Korea, so it is left out of the table. Sources: GWEC, Global Offshore Wind Report 2026 pp. 36, 38 (PDF); end 2024 from GWEC, Global Offshore Wind Report 2025 p. 46.
China48.4 GW
United Kingdomabout 17.0 GW
Germanyabout 9.6 GW
Netherlandsabout 4.9 GW
Taiwan3.6 GW
Denmarkabout 2.7 GW
Belgiumabout 2.2 GW
Franceabout 1.9 GW
Vietnam0.9 GW
Japan0.3 GW
Cumulative capacity by country (end of 2025, GW). Same values as the table. "About" values are our calculation.

Global cumulative offshore wind capacity, 2024-2025

Year endWorld cumulative (GW)New that year (GW)China cumulative (GW)Source
End 202483.2841.8GWEC 2025
End 202592.59.348.4GWEC 2026
Only values given in the text of each GWEC report are shown. New capacity of 8 GW in 2024 was 26% below the year before; 9.3 GW in 2025 was 16% above. Sources: GWEC 2025 p. 45, GWEC 2026 p. 35.
End 202483.2 GW
End 202592.5 GW
Global cumulative offshore wind capacity (GW). Same values as the table.

Auction volumes vary widely. Auctions and allocations reached a record 56.3 GW in 2024 (GWEC 2025 p. 48), but 11.4 GW was awarded in 2025, one fifth of 2024 (GWEC 2026 p. 11). GWEC expects 420 GW by the end of 2035 (p. 8). The IEA cut its global offshore wind forecast by 27% from the previous year, citing undersubscribed auctions and cancelled projects in several European markets and Japan amid US policy changes, macroeconomic pressure and supply chain problems (IEA, Renewables 2025).

Japan's offshore wind zones by prefecture (as of 5 January 2026)

ANRE's list as of 5 January 2026 shows 38 zones under the Act on Promoting the Utilisation of Sea Areas for Renewable Energy (renamed from 1 April 2026): 12 promotion zones, 9 promising zones and 17 preparatory zones, in 15 prefectures (ANRE, designation status of promotion and promising zones; prefecture count our calculation). MLIT's map as of June 2026 shows the same numbers (MLIT, 100th Ports and Harbours Subcommittee, Document 5 p. 1).

PrefecturePromotion zonesPromising zonesPreparatory zonesZones
Hokkaidooff Matsumae, off Hiyamaoff Ishikari City, off Ganu and Minami-Shiribeshi, off Shimamakioff Ganu and Minami-Shiribeshi (floating), off Shimamaki (floating)7
AomoriSea of Japan (south)Sea of Japan (north)Mutsu Bay3
Iwate--off Kuji City (floating)1
Akitaoff Noshiro, Mitane and Oga, off Yurihonjo City, off Happo and Noshiro, off Oga, Katagami and Akitaoff Akita City-5
Yamagataoff Yuza Townoff Sakata City-2
Niigataoff Murakami and Tainai--1
Chibaoff Choshi Cityoff Kujukuri, off Isumi Cityoff Asahi City4
Tokyo--off Oshima (floating), off Niijima (floating), off Kozushima (floating), off Miyake (floating), off Hachijo (floating)5
Toyama--eastern waters (floating)1
Fukui--off Awara City1
Wakayama--offshore (east), offshore (west, floating)2
Fukuoka-Hibikinada-1
Saga--off Karatsu City1
Nagasakioff Goto City (floating), off Enoshima, Saikai City-south of Goto City (floating)3
Kagoshima--off Ichikikushikino City1
Total (15 prefectures)12 zones9 zones17 zones38
Counts and totals are our calculation. Goto (floating) is marked "in operation" in the list. Hibikinada (Fukuoka) became a promising zone on 3 October 2025 (MLIT, 98th Ports and Harbours Subcommittee, Document 2 p. 1). Saga in bold. Source: ANRE, designation status (as of 5 January 2026).

On 8 October 2026, METI and MLIT announced that the state survey through JOGMEC (Japan Organization for Metals and Energy Security) would cover the waters off Wakayama (east) and off Ichikikushikino, Kagoshima, with an additional survey off Hiyama, Hokkaido (METI and MLIT).

Developers selected by round, 2021-2024

RoundZoneCapacity at selection (10 MW units)Supply price (¥/kWh)Planned startSelected developersSelected
Round 1off Goto, Nagasaki (floating)1.6836 (FIT)began operating Jan 2026Toda Corporation, ENEOS, Osaka Gas, INPEX, Kansai Electric Power, Chubu Electric Power2021-06-11
Round 1off Noshiro, Mitane and Oga, Akita49.413.26Dec 2028 (withdrawn)Mitsubishi Corporation Offshore Wind, Mitsubishi Corporation, C-Tech2021-12-24
Round 1off Yurihonjo, Akita84.511.99Dec 2030 (withdrawn)the same plus Wenty Japan2021-12-24
Round 1off Choshi, Chiba40.316.49Sep 2028 (withdrawn)Mitsubishi Corporation Offshore Wind, Mitsubishi Corporation, C-Tech2021-12-24
Round 2off Happo and Noshiro, Akita37.53Jun 2029ENEOS Renewable Energy, Iberdrola, Tohoku Electric Power2024-03-22
Round 2off Oga, Katagami and Akita, Akita31.53Jun 2028JERA, J-Power, Itochu, Tohoku Electric Power2023-12-13
Round 2off Murakami and Tainai, Niigata68.43Jun 2029Mitsui & Co., RWE, Osaka Gas2023-12-13
Round 2off Enoshima, Saikai, Nagasaki42.022.18Aug 2029Sumitomo Corporation, TEPCO Renewable Power2023-12-13
Round 3Sea of Japan (south), Aomori61.53Jun 2030JERA, Green Power Investment, Tohoku Electric Power-
Round 3off Yuza, Yamagata45.03Jun 2030Marubeni, Kansai Electric Power, BP, Tokyo Gas, Marutaka-
In Round 1, Goto (floating) was tendered separately from Mitsubishi Corporation's three sites. Development at those three sites was announced as stopped on 27 August 2025 (bold). Capacities in the list after withdrawal are 41.5, 73.0 and 37.0 (10 MW units). The document's figure gives about 1.8 GW for Round 2 and 1.1 GW for Round 3 (p. 9); the withdrawal from the three Round 1 sites delays 1.7 GW (p. 16). Sources: ANRE, Offshore wind power (26 Dec 2025) pp. 9, 16; MLIT Ports and Harbours Bureau.

Offshore wind farms operating in Japan (2026)

Wind farmLocationCapacityTurbinesStart of operationSource
Kitakyushu Hibikinada Offshore Wind FarmPort of Kitakyushu, Fukuokaabout 220,000 kW9.6 MW × 252 Mar 2026source
Ishikari Bay New Port Offshore WindIshikari Bay New Port, Hokkaidoabout 112,000 kW8 MW × 141 Jan 2024source
Noshiro Port Offshore WindPort of Noshiro, Akita84,000 kW4,200 kW × 20Dec 2022source
Akita Port Offshore WindPort of Akita, Akita54,600 kW4,200 kW × 13Jan 2023source
Goto Offshore Wind Farm (floating)off Goto City, Nagasakiabout 16,800 kW (16.8 MW)2.1 MW × 85 Jan 2026source
Largest first. The five total about 487 MW (our calculation). GWEC states that Japan's operating offshore wind exceeded 500 MW after Goto and Kitakyushu Hibikinada began operating (GWEC 2026 p. 89). Sources: MLIT, 100th Ports and Harbours Subcommittee, Document 5 p. 2; Akita Prefecture (as of 3 Oct 2025); MLIT Ports and Harbours Bureau.

Offshore wind installed under the feed-in tariff and premium schemes (FIT/FIP) totalled 490,275 kW at the end of June 2026 (ANRE, FIT public information website, Table A2-1, new certifications).

Environmental impact assessment for offshore wind

Under the Environmental Impact Assessment Act, wind farms of 50,000 kW or more must go through assessment (Class 1) and those of 37,500 kW to under 50,000 kW are judged case by case (Class 2) (Ministry of the Environment, projects subject to EIA). These thresholds come from an amended Cabinet Order in force from October 2021 (Ministry of the Environment, sea eagle bird-strike guidance (revised)).

As of December 2022, offshore wind had 86 primary environmental impact consideration documents and 10 draft environmental impact statements in total (Ministry of the Environment, study group report p. 5). The 2026 Annual Report on the Environment states that 922 EIA procedures had been carried out for all project types by the end of March 2026, that wind farms are among the projects with the most reviews, and that their environmental impact depends more on location than on scale. As offshore wind has little operating record and post-operation knowledge is limited, the Environment Minister's opinions call for follow-up surveys and additional conservation measures, and METI and the Ministry of the Environment published monitoring guidelines for offshore wind farms in September 2025 (Ministry of the Environment, Annual Report on the Environment 2026).

ItemContentSource
Class 1 (assessment required)50,000 kW or moreMOE
Class 2 (case by case)37,500 kW to under 50,000 kWMOE
Offshore wind: primary consideration documents86 (cumulative)MOE (Dec 2022)
Offshore wind: draft EIS10 (cumulative)MOE (Dec 2022)
Items assessed for fixed-bottomnoise, turbidity, birds, marine mammals, fish, benthic animals, seaweeds and seagrasses, landscape, etc.MOE
Items of particular concern in the Minister's opinionsnoise, birds, marine life, etc.MOE
Sources: MOE, projects subject to EIA; MOE, report of the FY2022 study group on EIA for offshore wind (March 2023) p. 5.

Offshore wind and birds: 73 sea eagle collisions and sensitivity maps

According to the Ministry of the Environment's guidance (revised August 2022), 73 bird strikes of White-tailed Eagles and Steller's Sea Eagles at wind farms were confirmed in the 19 years from FY2003 to FY2021. This is not a figure for offshore wind alone; it covers all wind farms, including onshore ones. Of the 73, 3 were Steller's and 70 White-tailed Eagles. Remains were reported at 39 medium to very large turbines (37 in Hokkaido, 2 in Aomori); the 37 in Hokkaido are 11.0% of the 336 medium to large turbines operating there. 60 of the 73 carcasses (82%) were found between October and April (MOE, sea eagle bird-strike guidance (revised) pp. 3, 19, 22). Seven collisions of sea eagles with small wind turbines were recorded from 2018 to March 2022 (p. 3). The ministry states that, as far as known, bird strikes at wind farms are the most common cause of death of the White-tailed Eagle, listed as Endangered (IB) (MOE, bird-strike prevention at wind farms).

The ministry published bird sensitivity maps for early-stage wind planning: the onshore version in March 2018 and the marine version on 26 March 2020. They use secondary grid squares of about 10 km; the marine version overlays protected areas, seabird colonies and seabird distribution at sea, in six levels (5 to 1 and "low") (MOE press release; MOE, report on creating the marine sensitivity map; viewable on EADAS).

Offshore wind and fisheries: how impacts are studied

A document of the council for the waters off Murakami and Tainai, Niigata divides fishery impacts into direct ones from restrictions on fishing and indirect ones through changes in marine life caused by underwater sound and other factors, with catch, fishing effort and CPUE (catch per unit effort) as indicators (Murakami-Tainai council, approach to fishery impact surveys). A Fisheries Agency commissioned report (March 2024) sets the basic survey periods at 1-2 years before development, about 1-2 years during construction and 3 years after operation starts, and notes that developers' EIAs generally do not survey fisheries (Fisheries Agency, survey of changes to nearby fishing grounds from new ocean development).

Decommissioning cost of offshore wind: 70% of offshore construction cost

The government's operational guidelines for the public tender system in general sea areas (revised June 2026) require tender plans to show how facilities will be removed and how removal costs will be secured after the occupancy permit ends or if the developer goes bankrupt, and state that selected developers will be required to put in place measures such as third-party guarantees to secure removal, including in bankruptcy. Tender plans are approved for 30 years in principle (METI and MLIT, operational guidelines pp. 5-6).

The Round 3 tender guidelines set the removal cost at the tender stage uniformly at 70% of offshore construction cost, to be reviewed after selection. The full removal cost must be secured from the start of operation until removal is complete, by a bank guarantee addressed to the government lodged by the start of operation or by deposit in an account ring-fenced in bankruptcy (or both). If it cannot be secured, the occupancy permit may be revoked (METI and MLIT, tender guidelines for Aomori (south) and Yuza, Yamagata pp. 8-9). The 70% is DNV GL's estimate of removal cost for fixed-bottom turbines (ANRE joint council document, Sep 2021, p. 29).

ItemContentSource
Removal method and how costs are securedshown in the tender planGuidelines pp. 5-6
Securing removalmeasures such as third-party guarantees, including in bankruptcy, made mandatoryGuidelines p. 6
Approval period of tender plan30 years in principleGuidelines p. 6
Removal cost at tender stage70% of offshore construction cost (uniform)Tender guidelines p. 8
How removal cost is securedbank guarantee to the government, or a ring-fenced accountTender guidelines p. 9
Decommissioning in generation cost (fixed-bottom)¥0.3/kWh (2023), ¥0.4/kWh (2040)Cost WG p. 28
Sources: METI and MLIT, operational guidelines (revised June 2026); METI and MLIT, Round 3 tender guidelines (Jan 2024); Generation Cost Verification Working Group (6 Feb 2025).

Withdrawal from offshore wind: Mitsubishi Corporation's three sites (2025)

According to government documents, the tender for the three Round 1 sites (off Noshiro, Mitane and Oga, Akita; off Yurihonjo, Akita; off Choshi, Chiba) opened on 27 November 2020, and a consortium led by Mitsubishi Corporation was selected on 24 December 2021. Mitsubishi Corporation decided and announced on 27 August 2025 that it would stop development. The government asked the company to respond sincerely to local communities and said it would examine the causes and review the tender system (ANRE, Offshore wind power, Oct 2025, p. 2, on the background to the three Round 1 projects).

ANRE's document states that, according to interviews with Mitsubishi Corporation, turbine procurement costs and offshore and onshore construction costs had each more than doubled from the estimates at the time of the tender (p. 14), and that the withdrawal delays 1.7 GW of capacity (p. 16) (ANRE, Offshore wind power, 26 Dec 2025). MLIT's map marks the three sites as "withdrawn, to be re-tendered" (MLIT, 98th Ports and Harbours Subcommittee, Document 2, 5 Nov 2025, p. 2). On 5 June 2026, METI and MLIT revised the operational guidelines, including setting an expected supply price range and revising the scoring of project feasibility (METI press release).

Generation cost of offshore wind: ¥30.9/kWh for fixed-bottom (2023)

The Generation Cost Verification Working Group (6 February 2025) estimates the cost of fixed-bottom offshore wind, including policy costs, at ¥30.9/kWh in 2023 and ¥13.5-14.3/kWh in 2040 (base case ¥14.0). The model plant is 350 MW with 25 years of operation and, for 2023, a 30% capacity factor (Generation Cost Verification Working Group, summary report p. 28).

Fixed-bottom offshore wind (¥/kWh)20232040 (base case)
Generation cost (incl. policy costs)30.914.0 (13.5-14.3)
Generation cost (excl. policy costs)21.19.8 (9.5-10.1)
of which construction11.35.5
of which operation and maintenance8.63.4
of which decommissioning0.30.4
of which policy cost equivalent to IRR8.54.0
Floating offshore wind in 2040 (reference) is ¥21.6-21.7/kWh including policy costs. Other sources in 2023 (incl. policy costs): utility solar 10.9, onshore wind 16.3, nuclear 12.6 or more, LNG 19.1, coal 24.8 ¥/kWh. Source: Generation Cost Verification Working Group (6 Feb 2025) pp. 4, 28, 30.

Offshore wind and wind power in Saga (2026)

The waters off Karatsu City in Saga remain a preparatory zone in the national list as of 5 January 2026 (ANRE), and also in MLIT's map as of June 2026 (MLIT, Document 5 p. 1). A briefing for residents was held at the Karatsu Citizens' Exchange Plaza on 29 March 2026 (Karatsu City, Q&A on offshore wind off Karatsu (Japanese)). Saga Prefecture's environmental white paper states that the prefecture asked the government to classify the area as a promising zone, but that in both FY2024 and FY2025 the classification was "reserved" (Saga Prefecture, Part 2: state of the environment (Japanese) p. 24). The history and the prefecture's Q&A are on Renewable energy and biodiversity.

Wind power installed in Saga under FIT/FIP totalled 65,401 kW at the end of June 2026, 0.92% of Japan; offshore wind was 0 kW (ANRE, FIT public information website; total and share our calculation).

Category (kW, end of June 2026)SagaJapan
New certifications, wind under 20 kW71.342,373.7
New certifications, wind 20 kW or more35,1605,019,841.4
of which offshore (new certifications)0490,275
Transitional certifications, wind under 20 kW07.1
Transitional certifications, wind 20 kW or more30,1702,047,687.8
Wind total (our calculation)65,401.37,109,910
Installed capacity of facilities certified under FIT/FIP; facilities outside the schemes are not included. Source: ANRE, FIT public information website Tables A2-1 and A2-2 (installed capacity by prefecture, end of June 2026).

An example from Karatsu (our work)

On 7 October 2026 we installed a small hydropower generator driven by the flow of an irrigation channel at Yokomakura in Ochi, Karatsu. Its electricity goes through a battery to an electric fence that keeps out wildlife. Output is being recorded. See green infrastructure (small hydropower and an electric fence at Yokomakura).

For site visits, training or corporate partnerships at Yokomakura, see "Citing this page and enquiries" below.

Frequently asked questions

Q1. What are the disadvantages of offshore wind power?

A Ministry of the Environment study group report (March 2023) lists noise, turbidity, birds, marine mammals, fish, benthic animals, seaweeds and seagrasses, and landscape among the items assessed for fixed-bottom offshore wind, and names noise, birds and marine life as items of particular concern. Government documents also deal with securing decommissioning costs and with withdrawals caused by rising costs.

Q2. Which countries have the most offshore wind?

At the end of 2025 the world had 92.5 GW. Shares: 1 China 52.3%, 2 United Kingdom 18.4%, 3 Germany 10.4%, 4 Netherlands 5.3%, 5 Taiwan 3.9% (GWEC 2026, sorted by us). Japan had 0.3 GW.

Q3. Why did Mitsubishi Corporation withdraw from offshore wind in Japan?

ANRE's document (26 Dec 2025) states that, according to interviews with the company, turbine procurement costs and offshore and onshore construction costs had each more than doubled from the estimates at the time of the tender. The stop was announced on 27 August 2025, delaying 1.7 GW.

Q4. Where is offshore wind operating in Japan?

Five farms: Kitakyushu Hibikinada (about 220 MW), Ishikari Bay New Port (about 112 MW), Noshiro Port (84 MW), Akita Port (54.6 MW) and floating Goto (about 16.8 MW), about 487 MW in total (our calculation). As of 5 January 2026 there were 12 promotion, 9 promising and 17 preparatory zones.

Q5. Does offshore wind affect birds?

The Ministry of the Environment's guidance records 73 collisions of White-tailed and Steller's Sea Eagles with wind farms in FY2003-FY2021, a figure covering all wind farms including onshore ones. The ministry publishes bird sensitivity maps for early planning (marine version 2020).

Q6. Who pays to remove offshore wind farms?

The selected developer. The government's guidelines make measures to secure removal, including in bankruptcy, mandatory; the Round 3 tender guidelines set the tender-stage removal cost at 70% of offshore construction cost, secured in full by a bank guarantee or a ring-fenced account.

Q7. How much does offshore wind power cost?

The Generation Cost Verification Working Group (Feb 2025) estimates fixed-bottom offshore wind at ¥30.9/kWh in 2023 and ¥14.0/kWh in 2040 (base case), including policy costs. Utility solar was ¥10.9 and onshore wind ¥16.3/kWh in 2023.

Q8. What is happening with offshore wind off Karatsu?

The area remains a preparatory zone in the national list as of 5 January 2026. A briefing for residents was held in Karatsu on 29 March 2026. The history is on our Renewable energy and biodiversity page.

Source register

DocumentPublisherDateURLAccessed
Global Offshore Wind Report 2026GWEC (Global Wind Energy Council)2026-06-09https://www.gwec.net/reports/globaloffshorewindreport2026-11-20
Global Offshore Wind Report 2026 (PDF, third-party copy)GWEC2026-06-09https://gowa-energy.org/files/media/document/GWEC%20Global%20Offshore%20Wind%20Report%202026.pdf2026-11-20
Global Offshore Wind Report 2025 (PDF, copy on PNNL Tethys)GWEC2025-06https://tethys.pnnl.gov/sites/default/files/publications/Williams-et-al-2025.pdf2026-11-20
Renewables 2025: Renewable electricityIEA (International Energy Agency)2025-10https://www.iea.org/reports/renewables-2025/renewable-electricity2026-11-20
Designation status of promotion and promising zones (as of 5 Jan 2026)ANREas of 2026-01-05https://www.enecho.meti.go.jp/category/saving_and_new/saiene/yojo_furyoku/dl/saiene_kaiiki_gaiyou.pdf2026-11-20
Offshore wind power (Document 2, renewable energy subcommittee)ANRE2025-12-26https://www.meti.go.jp/shingikai/enecho/denryoku_gas/saisei_kano/pdf/078_02_00.pdf2026-11-20
Offshore wind power (Reference 1; p. 2 on the background to the three Round 1 projects won by the Mitsubishi Corporation consortium)ANRE2025-10https://www.meti.go.jp/shingikai/santeii/pdf/104_s01_00.pdf2026-11-20
100th Ports and Harbours Subcommittee, Document 5MLIT2026-06-23https://www.mlit.go.jp/policy/shingikai/content/002008233.pdf2026-11-20
98th Ports and Harbours Subcommittee, Document 2MLIT2025-11-05https://www.mlit.go.jp/policy/shingikai/content/001967825.pdf2026-11-20
Reference material on offshore windMLIT Ports and Harbours Bureauhttps://www.mlit.go.jp/kowan/content/001879076.pdf2026-11-20
Status of offshore wind (as of 3 Oct 2025)Akita Prefecture2025-10-03https://www.pref.akita.lg.jp/uploads/public/archive_0000007451_00/2.%E6%B4%8B%E4%B8%8A%E9%A2%A8%E5%8A%9B%E7%99%BA%E9%9B%BB%E3%81%AE%E5%B0%8E%E5%85%A5%E7%8A%B6%E6%B3%81%EF%BC%88202510%EF%BC%89.pdf2026-11-20
Selection of zones for JOGMEC site surveysMETI and MLIT2026-10-08https://www.meti.go.jp/press/2026/10/20261008001.html2026-11-20
Revision of the operational guidelines for the public tender system in general sea areasMETI and MLIT2026-06-05https://www.meti.go.jp/press/2026/06/20260605004/20260605004.html2026-11-20
Operational guidelines for the public tender system in general sea areasMETI and MLIT2026-06https://www.enecho.meti.go.jp/category/saving_and_new/saiene/yojo_furyoku/dl/legal/operation_kaitei.pdf2026-11-20
Tender guidelines for Aomori (Sea of Japan, south) and off Yuza, YamagataMETI and MLIT2024-01https://www.mlit.go.jp/kowan/content/001745625.pdf2026-11-20
Joint council document on offshore wind (decommissioning cost)ANRE2021-09https://www.meti.go.jp/shingikai/enecho/denryoku_gas/saisei_kano/yojo_furyoku/pdf/009_01_00.pdf2026-11-20
1-4 Projects subject to environmental impact assessmentMinistry of the Environmentrevised 2022-04-01https://assess.env.go.jp/1_seido/1-1_guide/1-4.html2026-11-20
Report of the FY2022 study group on EIA for offshore windMinistry of the Environment2023-03https://www.env.go.jp/council/content/i_01/000170048.pdf2026-11-20
Annual Report on the Environment 2026, Part 2, Ch. 6, Sec. 7Ministry of the Environment2026https://www.env.go.jp/policy/hakusyo/r08/html/hj26020607.html2026-11-20
Guidance on preventing sea eagle bird strikes at wind farms (revised)Ministry of the Environment2022-08https://www.env.go.jp/content/000062920.pdf2026-11-20
Release of the marine bird sensitivity map for wind powerMinistry of the Environment2020-03-26https://www.env.go.jp/press/107900.html2026-11-20
Report on creating the marine bird sensitivity map for wind powerMinistry of the Environmenthttps://www.env.go.jp/content/900494239.pdf2026-11-20
Bird-strike prevention at wind farmsMinistry of the Environmenthttps://www.env.go.jp/nature/yasei/sg_windplant/birdstrike.html2026-11-20
Survey of changes to nearby fishing grounds from new ocean developmentFisheries Agency2024-03https://www.jfa.maff.go.jp/j/gyoko_gyozyo/g_thema/houkokusho/attach/pdf/R5houkokusho-17.pdf2026-11-20
Approach to fishery impact surveys (Murakami-Tainai council)ANREhttps://www.enecho.meti.go.jp/category/saving_and_new/saiene/yojo_furyoku/dl/kyougi/niigata_murakami/03_docs03.pdf2026-11-20
Summary report of the generation cost verificationGeneration Cost Verification Working Group2025-02-06https://www.enecho.meti.go.jp/committee/council/basic_policy_subcommittee/mitoshi/cost_wg/pdf/cost_wg_20250206_01.pdf2026-11-20
FIT public information website, Table A: certification and installation by prefecture (end of June 2026)ANREas of end 2026-06https://www.fit-portal.go.jp/PublicInfoSummary2026-11-20
Q&A on offshore wind off KaratsuKaratsu Cityupdated 2026-09-07https://www.city.karatsu.lg.jp/page/51577.html2026-11-20
Part 2: state of the environment and measures (environmental white paper)Saga Prefecturehttps://www.pref.saga.lg.jp/kiji003119679/3_119679_392437_up_qbxvd1n5.pdf2026-11-20

Notes on reading the figures

GWEC shows cumulative capacity by country only as pie-chart shares, with no table. GW values by country, except those given in the text (China, Taiwan, Vietnam, Japan, South Korea), are 92.5 GW × share calculated by us, and the ranks are our sorting. The global trend shows only the years given in the text of GWEC's 2025 and 2026 reports. The GWEC 2026 PDF was obtained from a third-party copy. The 73 sea eagle collisions cover all wind farms, including onshore, not offshore wind alone. The zone list is as of 5 January 2026, and the document notes that capacities may change. Saga's wind capacity covers only facilities certified under FIT/FIP. Generation costs are estimates, not actual project costs.

What this page does not cover

A review of research on ecological impacts of offshore wind, the history of the waters off Karatsu and Saga Prefecture's Q&A are on Renewable energy and biodiversity; greenhouse gas emissions are on CO2 emissions and decarbonisation; green infrastructure figures are on green infrastructure data. This page does not assess individual projects or cover floating wind technology, effects on electricity prices or landscape simulations.

Citing this page and enquiries

To cite figures from this page, or to ask about visiting the small hydropower generator and electric fence at Yokomakura, training or corporate partnerships, please use our contact page or write to info@karatsu-f-f.com.

About this page

By Hiroaki Kojima (Vice Director, Karatsu Farm & Food) / Contact: info@karatsu-f-f.com (contact page) / Published: 20 November 2026 / Markdown: offshore-wind-data.md

This page is made together with AI. See this data bank and AI for how.

Related links

▶ Karatsu Data Bank
▶ Renewable energy and biodiversity
▶ Green infrastructure: small hydropower and an electric fence at Yokomakura
▶ Green infrastructure data
▶ CO2 emissions and decarbonisation
▶ 洋上風力発電のデメリット・問題点と導入量2026(日本語)

  • Address
  • 847-0017
  • 3-7-22 Higashi-Karatsu, Karatsu City, Saga, Japan